Lim Wen Heng Construction Pte Ltd began its history as a private limited company in Singapore in 1994. Under the stewardship of its pioneers and a team of professionals with a vision of growth and quality excellence, the company is growing and establishing itself as one of the construction specialists in the Singapore construction industry. Our major activities are in General Building Construction and other Civil Engineering works. We are registered with the Building & Construction Authority BCA’s Registry of Contractors. Our staff and workers are highly qualified and motivated and we are committed to satisfying our clients’ requiremednts.
Featured Project

Eon Shenton
Location of Eon Shenton project is the most challenge part that we faced during our construction period. The building can be described as an island surrounded by Shenton Way Road, Palmer Road, Mistri Road and Parsi Road. There is limited loading and unloading area and storage space at site with only 1,840 m2 site area. We overcame the constraint with implementing proper safety and traffic control system to ensure public safety is totally protected.
Vertical and horizontal system formwork, prefabricated columns, wall and slab reinforcement were among a few value engineering implemented to expedite construction cycle for this high-rise building. With cooperation among site construction team, 6 days cycle per floor was achieved to offer shorter construction period.
Unitised aluminium cladding wall system was implemented at 2nd storey to 6th storey external façade work to speed up cladding wall installation during construction period with excellence aesthetic view.

Liv on Wilkie
The development is at the edge of Emily Hill which is 8 meter difference in height. The neighbour’s land was protected by injection soil nail cable into their ground.
Another challenge we faced was to build two level of basement with the depth of 9 meter below ground level. Perimeter of boundary were supported by contiguous bore piling system. We adopted top-down construction methodology built from ground level downward to two level of basement and followed by construction of the super structure tower block.
The soil underneath is full of rocks and boulders, excavation is done using hydraulic twister instead of hydraulic breaker to remove them.